Energy Efficiency Upgrades for Fermilab Infrastructure: Federal Energy Management Program (FEMP) Utility Services Case Study (Fact sheet)

    Research output: NRELFact Sheet

    Abstract

    At the Fermi National Accelerator Laboratory (Fermilab), originally built in the 1960s, old process and comfort chillers, pumps, and other related central cooling-system equipment were replaced, and pumping configuration changes were made to accelerator heat rejection systems. The employee office space and a 'process system' for the equipment and accelerators. The new 4500-ton cooling system isexpected to use 40% less energy and is free of ozone-depleting chlorofluorocarbons. Energy savings of 20 million kWh and a deamnd reduction of about 2.5 megawatts are expected, resulting in estimated cost savings of $900,000 per year.
    Original languageAmerican English
    Number of pages2
    StatePublished - 2000

    NREL Publication Number

    • NREL/FS-710-26810

    Other Report Number

    • DOE/GO-10200-0920

    Fingerprint

    Dive into the research topics of 'Energy Efficiency Upgrades for Fermilab Infrastructure: Federal Energy Management Program (FEMP) Utility Services Case Study (Fact sheet)'. Together they form a unique fingerprint.

    Cite this