This report covers testing of General Electric-proposed anti-islanding schemes. The objectives were to: 1) Validate the effectiveness of the proposed anti-islanding schemes; 2) Conduct parametric evaluation of the schemes with respect to control settings and load conditions, including controller gains, load power levels, and load quality factors; and 3) Examine the ability of the distributedresource to ride through a low-voltage condition on the utility grid.
Original language | American English |
---|---|
Number of pages | 24 |
DOIs | |
State | Published - 2005 |
NREL Publication Number
- NREL/TP-560-37200
Keywords
- anti-islanding
- DER
- DG
- distributed energy
- distributed power
- distributed resources
- GE
- General Electric (GE)
- IEEE 1547
- interconnection
- inverter
- low-voltage ride-through
- National Renewable Energy Laboratory (NREL)
- NREL