Abstract
Solar Two was a 10-MWe prototype central receiver plant east of Barstow, California. Solar Two, which was sponsored by a consortium of utilities and industry in partnership with the U.S. Department of Energy, began regular electricity production in February 1997 and completed its last day of regular electricity production in March 1999. This paper presents preliminary results from the most recentSolar Two performance evaluation.
Original language | American English |
---|---|
Pages | 613-619 |
Number of pages | 7 |
State | Published - 1999 |
Event | IECEC 1999: 34th Intersociety Energy Conversion Engineering Conference - Vancouver, British Columbia Duration: 2 Aug 1999 → 5 Aug 1999 |
Conference
Conference | IECEC 1999: 34th Intersociety Energy Conversion Engineering Conference |
---|---|
City | Vancouver, British Columbia |
Period | 2/08/99 → 5/08/99 |
NREL Publication Number
- NREL/CP-550-27908