Abstract
This white paper evaluates the origins and usefulness of the capacity penetration screen, offer short-term solutions which could effectively allow fast-track interconnection to many PV system applications, and considers longer-term solutions for increasing PV deployment levels in a safe and reliable manner while reducing or eliminating the emphasis on the penetration screen. Short-term andlonger-term alternatives approaches are offered as examples; however, specific modifications to screening procedures should be discussed with stakeholders and must ultimately be adopted by state and federal regulatory bodies.
Original language | American English |
---|---|
Number of pages | 21 |
DOIs | |
State | Published - 2012 |
NREL Publication Number
- NREL/TP-5500-54063
Keywords
- 15% threshold
- CPUC rule 21
- FERC SGIP
- high penetration PV
- IEEE 1547
- IEEE 1547.8
- peak loads
- unintentional islanding